Belgian marine firm hired for offshore trenching on the Prince Rupert Gas Transmission line, with work starting next year

DEME Group will dig trenches in Nass Bay, Iceberg Bay, Nasoga Gulf and Wil Milit. The pipeline would feed the Ksi Lisims LNG terminal.

Published Nov 26, 2026 in Prince Rupert
By The NWBC Current newsroom
A pipe-laying vessel at sea (file photo from Scotland)
Photo: David Dixon via Wikimedia Commons, CC BY-SA 2.0 (source)

A second European contractor has signed on to marine construction for the Prince Rupert Gas Transmission pipeline, CFNR reports.

Western LNG gave the main offshore contract to Swiss firm Allseas in July. Allseas has now subcontracted pre-trenching in Nass Bay, Iceberg Bay, Nasoga Gulf and Wil Milit to Belgium-based DEME Group. The value was not announced, but DEME describes it as a "large" contract, a category it uses for deals over 300 million dollars.

DEME's work is set to start next year. Allseas would then lay the pipe in two campaigns beginning in 2029. The offshore section covers about 50 of the line's 750 kilometres, at depths of up to 450 metres. The pipeline is meant to supply the Nisga'a Nation's Ksi Lisims LNG terminal, planned to produce 12 million tonnes a year.

Sources: CFNR Network, Second European contractor hired to undertake offshore works for Prince Rupert Gas Transmission Pipeline, Nov. 26, 2026, Ksi Lisims LNG.